How to answer the question \"When will it be ready?\" based on statistics

Anastasia Zhadrinskaya10 Oct 2023

Problem

Teams keep being asked "when will it be ready?" and usually answer with expert estimates. Experts count only the hands-on time of a task, yet in IT most of the elapsed time goes to waiting and blockers, so the estimates miss.

Example from the article: a team wants to know when it will finish 80 Features, and has a year of monthly counts of closed Features.

Solution in brief

Take the team's historical throughput (tasks closed per period) and run a Monte Carlo simulation on it, using an Excel workbook. The output is a table of completion dates with a probability for each, so you can commit to a date whose risk you accept. Re-run it every week as new data arrives.

Questions this case answers
  • How to forecast the completion date of a fixed amount of work from the history of completed items without per-item expert estimates
  • How to turn a forecast into a commitment by choosing an acceptable probability of missing the date
  • How to tell stakeholders when a backlog of N tasks will be finished, with a stated probability
  • How to forecast delivery dates from a team's historical throughput instead of expert estimates

Tools and methods

  • Monte Carlo simulation — repeats a randomized model of future throughput thousands of times and reads dates off the distribution
  • Throughput Forecaster.xlsx (Troy Magennis) — the workbook that does the simulation
  • Jira Flow Companion (Chrome extension) — Throughput report and a built-in Monte Carlo view for a Jira board
  • Jira — source of closed-task counts