Problem
Teams keep being asked "when will it be ready?" and usually answer with expert estimates. Experts count only the hands-on time of a task, yet in IT most of the elapsed time goes to waiting and blockers, so the estimates miss.
Example from the article: a team wants to know when it will finish 80 Features, and has a year of monthly counts of closed Features.
Solution in brief
Take the team's historical throughput (tasks closed per period) and run a Monte Carlo simulation on it, using an Excel workbook. The output is a table of completion dates with a probability for each, so you can commit to a date whose risk you accept. Re-run it every week as new data arrives.
Questions this case answers
- How to forecast the completion date of a fixed amount of work from the history of completed items without per-item expert estimates
- How to turn a forecast into a commitment by choosing an acceptable probability of missing the date
- How to tell stakeholders when a backlog of N tasks will be finished, with a stated probability
- How to forecast delivery dates from a team's historical throughput instead of expert estimates
Tools and methods
- Monte Carlo simulation — repeats a randomized model of future throughput thousands of times and reads dates off the distribution
- Throughput Forecaster.xlsx (Troy Magennis) — the workbook that does the simulation
- Jira Flow Companion (Chrome extension) — Throughput report and a built-in Monte Carlo view for a Jira board
- Jira — source of closed-task counts