Problem
Product and IT teams are asked «when will this be done?» and usually answer with Story Points or person-hours. At T-Bank the author checked whether such estimates predict actual duration, and they do not. Missed dates come from the delivery system (waiting on other tasks, blockers from other teams, neglected tasks), which an estimate of the task alone cannot see.
Example from the article: in several T-Bank teams that use Story Points, the lead-time distributions of 1-, 2-, 3-, 4- and 5-point stories almost coincide, with lead time ranging from 1 to 302 days.
Solution in brief
Replace the open question «when?» with the closed one «will we finish by date X?». Limit work in progress, filter incoming tasks by risk, keep the process stable (watch it on a control chart), and read the answer from the empirical lead-time distribution per work type: take the 85th or 95th percentile as the commitment and compute the chance of meeting a given deadline.
Questions this case answers
- How to forecast the completion time of heterogeneous work items from historical timestamps when expert estimates do not correlate with actual duration
- How to detect that a process generating the durations has drifted, so that past statistics no longer support a forecast
- How to answer a customer's question «when will it be done?» with a deadline you can actually meet
- How to check whether Story Point or person-hour estimates predict real completion time
Tools and methods
- Lead Time distribution — time from the team's commitment (To Do) to delivery (Released), plotted per work type
- Percentile commitment (85%/95%) — the deadline the team can promise
- WIP / CONWIP limits, Capacity Allocation — make the delivery process predictable
- Control chart — shows drift and exceptional tasks
- Cynefin categories (Simple, Complicated, Complex, Chaos) — sort incoming tasks by risk