How the total changes when you swap places in a production schedule

16 May 2023

Problem

Planners at the NLMK-Kaluga steel plant built loading plans in Excel for the rolling mill and the continuous casting machine (CCM). Each unit works around the clock and makes one product type at a time. Switching between rebar diameters takes the longest, so the order of orders drives lost time. Plans depended on planner experience, and some orders were forgotten. Scale: about 125,000 t of steel a month, 80,000 t of it rebar.

Example from the article: in October 2021 the plant had 48 product types. Grouping orders by type alone gives 48! possible sequences, far too many to enumerate.

Solution in brief

Model each production run as an interval variable and let a constraint solver (IBM CPLEX with OPL) arrange the intervals under the plant's rules. A .NET service feeds it orders, stock and shipments from ERP and MES, then turns the Gantt result into daily shift tasks. The rolling shop is planned first, and the steelmaking shop second.

Questions this case answers
  • How to sequence orders on a single sequential-use machine so that setup time between product types is minimized while due dates and calendar rules (no starts on some days, fixed maintenance windows) still hold
  • How to plan two dependent production stages so that the upstream stage delivers its intermediate product just in time for the downstream stage
  • How to sequence customer orders on a rolling mill so that equipment changeovers are minimized and shipment dates are still met?
  • How to replace manual Excel production plans with an optimizer that respects weekday, export-grade and maintenance rules?

Tools and methods

  • IBM CPLEX — solver with interval variables, OPL for the model
  • SAP — source of sales orders; calculated shipment dates go back to it
  • Combinatorial optimization — sequencing orders to cut changeovers under constraints