Problem
A combined heat and power plant at a steel works generates electricity with turbogenerators. Each turbogenerator exhausts its steam into a condenser, a box of about 5 thousand thin tubes. Sand, silt and shells foul the tubes, the vacuum drops, and the turbine makes less power from the same steam. Cleaning needs a stop or a load reduction, which also costs generation. Clean too early and you lose output for nothing. Clean too late and every kilowatt-hour costs more. The plant cleaned by schedule, running hours and season, or when performance visibly worsened, and wanted the best day.
Example from the article: integrators proposed comparing plant data with a theoretical physical model or operating-mode charts. The team judged both too complex to maintain and too inaccurate for its sensors.
Solution in brief
Model profit per hour as electricity revenue minus steam cost, where steam cost grows linearly after each cleaning. Differentiate the cost model, set the derivative to zero and clean at the extremum. Several indirect fouling indicators (heat transfer coefficient, vacuum, cooling-water flow and others) confirm the verdict.
Questions this case answers
- How to choose the optimal time to service degrading equipment when service itself causes a production loss
- How to estimate an unmeasurable process quantity from a balance equation when the available sensors are noisy
- How to choose the day to stop a turbogenerator for condenser cleaning when cleaning costs generation?
- How to detect fouling of a heat exchanger when there are no flow meters on the cooling-water lines?
Tools and methods
- Cost-versus-time optimization — picks the cleaning moment from the profit curve
- Condenser heat balance — replaces the missing cooling-water flow meter
- Fouling indicators — heat transfer coefficient, vacuum, specific heat consumption, each against its own reference