Problem
Severstal's Metal Finishing Shop No. 2 cuts steel coils into sheets and strips on five units. Planners built the cutting schedule by hand in DELMIA Quintiq, which took 5 to 8 hours and caused fatigue and errors. A campaign is a group of coils cut in a row on one unit with no changeover inside. It must respect campaign rules, changeover times, railcar fill norms and delivery dates. The search space is too large to solve in one step, and users wanted a plan within 20 minutes.
Example from the article: one planning run covers 1,500 to 4,000 coils over a horizon of one to three days. Sixty suitable coils and a campaign size of 20 already give 4,191,844,505,805,495 possible campaign selections.
Solution in brief
The team split the task into two parts. A mixed integer programming (MIP) model groups coils into campaigns and railcars from pre-built candidates. A path optimization algorithm (POA) then orders the coils on each unit. Shifts are solved one by one, and every candidate is scored by one weighted sum of 15 KPIs.
Questions this case answers
- How to build a schedule optimizer for a combinatorial problem that mixes grouping items into batches with sequencing them, when the full model is too large to solve in the allowed time
- How to encode the tacit preferences of human planners into a weighted objective so that an automatic plan matches what they would accept
- How to automate shift scheduling of coil cutting when planners spend 5 to 8 hours building it by hand?
- How to split a huge combinatorial scheduling problem into subproblems that solve within a 20-minute limit?
Tools and methods
- Mixed integer programming (MIP) — chooses railcar types and candidate campaigns ("combis")
- Path optimization algorithm (POA) — sequence coils on each unit to minimize changeovers
- Weighted KPI objective — rank any candidate plan by one number
- Planners' soft knowledge — drops bad candidates before solving